Is it necessary to prove capacity bookings when biomethane is transported via the gas grid?

Modified on Thu, 1 May at 4:31 PM

The following documentation is sufficient for mass balance reporting of biomethane transport through connected gas grids: 

  1. Delivery invoices/contracts that cover the respective amounts of biomethane. 

  2. Verification of the physical connection between input and output points, e.g., using a gas grid map.