How do I know when my registration is ready for Audit?

Modified on Wed, 11 Nov at 9:48 AM

A registration is officially finalized only after you receive the formal registration confirmation email from ISCC.

Before this email can be sent, two approvals must happen in the ISCC HUB:

  • Your Certification Body (CB) reviews and approves the registration.

  • ISCC completes the final review and approves it.

Once ISCC sends out the confirmation email, the registration process is complete and you are officially clear to proceed with the audit.

Important: Audits cannot take place before registration is finalized Conducting an audit before receiving the registration confirmation email is a direct violation of:

  • ISCC Terms of Use (Section 3.6)

  • ISCC System Documents (ISCC 201 System Basics, Chapter 4.1)

The contractual agreement between ISCC and the System User only takes effect once the confirmation email is issued. Starting an audit before this point is considered non-compliant and can result in further consequences.

What you need to do

  • For Certification Bodies: Please review and approve pending registrations in the HUB as early as possible so ISCC has enough time to finalize the registration before the planned audit date.

  • For System Users: Make sure your audit team and relevant colleagues are aware of this rule so audits are not scheduled prematurely.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article